Update 6 October 2022

Stage One works are progressing despite delays due to inclement weather and delivery of materials. Installation of the furniture and play elements is almost complete and work has commenced on installing a range of rocks and natural materials for retaining, as well as decorative fencing panels along the northern edge. Construction of the new footbridge is being finalised offsite before being installed at the northern side of the Oval closer to project completion. It is expected Stage One works will be completed by the end of November 2022. 

Stage Two works will include a new and upgraded grandstand, changerooms, meeting rooms and function area along with carparking and additional recreation elements. Consultants continue to work with the City of West Torrens (CWT) and the West Adelaide Football Club (WAFC) on the planning and concept design of this next stage of works. 

On 2 September 2022, a site tour was arranged and attended by consultants, members of the WAFC and a number of CWT staff and Elected Members to inform the design of the project. 

The following sites were visited: 

  • SA Cricket Association Sports Hub, Karen Rolton Oval; 
  • Campbelltown Memorial Oval Sports Hub, Paradise; and 
  • Football Federation of SA - State Centre of Football, Gepps Cross. 

Consultants will now consolidate feedback from the tour along with comments received from the public consultation undertaken earlier this year, and develop draft concept/preliminary design plan for the next stage of works. This concept/preliminary design plan will be presented to Council in early 2023 for comment. 




To meet the growing needs of our community and provide improved, user-friendly recreational spaces, the City of West Torrens has developed a master plan focussed on the redevelopment of Richmond Oval.

The Master Plan aims to provide a sustainable, high-quality public open space which is user-friendly for local residents while also offering multi-user sporting and recreational activities and opportunities.  

Key features proposed for the overarching Master Plan include:

  • improved accessibility
  • activation of community open space including:
    - netball courts and 3-on-3 basketball court
    - new playground/activity area in the north-eastern corner
    - cricket nets plus storage
    - toilet facilities in the south-eastern corner
    - bike track/running track around the external perimeter of the oval
  • multi-use oval 
  • improved pedestrian and cycling access points at Martin and Kingston Avenues
  • upgraded terrace seating
  • improved overflow car parking and recreation/training area
  • improved football club change rooms, umpire rooms and match day coaches area
  • function area and meeting room(s) for community use.


Stage 2 - have your say!

Now that consultation on Stage 1 (focussing on the eastern side of the oval) is complete, we are now seeking community feedback on the Stage 2 Master Plan which will focus on the western side of the oval. This Master Plan may include:

  • upgraded grandstand
  • function area
  • unisex changerooms
  • meeting rooms
  • carparking
  • netball courts.


View documents 


How to have your say

Provide your feedback using any of the following:

  • Online
    Complete the online survey  at the bottom of this page.

  • Community Open Day
    Council staff will be in attendance to answer questions, note concerns and receive comments on the master plan. 

    When: 9.30am - 11am, Saturday 27 November 2021
    Where: Premiership Park, Milner Rd, Richmond 

  • Post
    Complete the hard copy survey or prepare a written submission (addressing the questions in the hard copy survey) and mail to:
    'Stage 2 Richmond Oval redevelopment feedback'
    City of West Torrens
    165 Sir Donald Bradman Drive
    Hilton 5033


  • Email
    Complete the hard copy survey or prepare a written submission (addressing the questions in the hard copy survey) and email csu@wtcc.sa.gov.au with the subject heading 'Stage 2 Richmond Oval redevelopment feedback'. 


All responses must be received by 5pm Tuesday 4 January 2022.

Note: written submissions will become public record, including forming part of a report to Council, and as such personal information, such as names and addresses, may become part of that publicly available information. If you have any questions about this, please contact our Manager Financial Services on the number listed. 


Additional information

Community Planner on 8416 6347 / email tdesteno@wtcc.sa.gov.auExternal link).



Join the conversation today
Create an account or login to share your thoughts, feedback and ideas.






If you'd rather not create an account, you can still provide feedback using the hard copy survey.

Richmond Oval
57 Milner Road, Richmond



Update 6 October 2022

Stage One works are progressing despite delays due to inclement weather and delivery of materials. Installation of the furniture and play elements is almost complete and work has commenced on installing a range of rocks and natural materials for retaining, as well as decorative fencing panels along the northern edge. Construction of the new footbridge is being finalised offsite before being installed at the northern side of the Oval closer to project completion. It is expected Stage One works will be completed by the end of November 2022. 

Stage Two works will include a new and upgraded grandstand, changerooms, meeting rooms and function area along with carparking and additional recreation elements. Consultants continue to work with the City of West Torrens (CWT) and the West Adelaide Football Club (WAFC) on the planning and concept design of this next stage of works. 

On 2 September 2022, a site tour was arranged and attended by consultants, members of the WAFC and a number of CWT staff and Elected Members to inform the design of the project. 

The following sites were visited: 

  • SA Cricket Association Sports Hub, Karen Rolton Oval; 
  • Campbelltown Memorial Oval Sports Hub, Paradise; and 
  • Football Federation of SA - State Centre of Football, Gepps Cross. 

Consultants will now consolidate feedback from the tour along with comments received from the public consultation undertaken earlier this year, and develop draft concept/preliminary design plan for the next stage of works. This concept/preliminary design plan will be presented to Council in early 2023 for comment. 




To meet the growing needs of our community and provide improved, user-friendly recreational spaces, the City of West Torrens has developed a master plan focussed on the redevelopment of Richmond Oval.

The Master Plan aims to provide a sustainable, high-quality public open space which is user-friendly for local residents while also offering multi-user sporting and recreational activities and opportunities.  

Key features proposed for the overarching Master Plan include:

  • improved accessibility
  • activation of community open space including:
    - netball courts and 3-on-3 basketball court
    - new playground/activity area in the north-eastern corner
    - cricket nets plus storage
    - toilet facilities in the south-eastern corner
    - bike track/running track around the external perimeter of the oval
  • multi-use oval 
  • improved pedestrian and cycling access points at Martin and Kingston Avenues
  • upgraded terrace seating
  • improved overflow car parking and recreation/training area
  • improved football club change rooms, umpire rooms and match day coaches area
  • function area and meeting room(s) for community use.


Stage 2 - have your say!

Now that consultation on Stage 1 (focussing on the eastern side of the oval) is complete, we are now seeking community feedback on the Stage 2 Master Plan which will focus on the western side of the oval. This Master Plan may include:

  • upgraded grandstand
  • function area
  • unisex changerooms
  • meeting rooms
  • carparking
  • netball courts.


View documents 


How to have your say

Provide your feedback using any of the following:

  • Online
    Complete the online survey  at the bottom of this page.

  • Community Open Day
    Council staff will be in attendance to answer questions, note concerns and receive comments on the master plan. 

    When: 9.30am - 11am, Saturday 27 November 2021
    Where: Premiership Park, Milner Rd, Richmond 

  • Post
    Complete the hard copy survey or prepare a written submission (addressing the questions in the hard copy survey) and mail to:
    'Stage 2 Richmond Oval redevelopment feedback'
    City of West Torrens
    165 Sir Donald Bradman Drive
    Hilton 5033


  • Email
    Complete the hard copy survey or prepare a written submission (addressing the questions in the hard copy survey) and email csu@wtcc.sa.gov.au with the subject heading 'Stage 2 Richmond Oval redevelopment feedback'. 


All responses must be received by 5pm Tuesday 4 January 2022.

Note: written submissions will become public record, including forming part of a report to Council, and as such personal information, such as names and addresses, may become part of that publicly available information. If you have any questions about this, please contact our Manager Financial Services on the number listed. 


Additional information

Community Planner on 8416 6347 / email tdesteno@wtcc.sa.gov.auExternal link).



Join the conversation today
Create an account or login to share your thoughts, feedback and ideas.






If you'd rather not create an account, you can still provide feedback using the hard copy survey.
  • CLOSED: This survey has concluded.

    Survey closed.

    Council is now seeking community feedback on the Stage 2 Master Plan which will focus on the western side of the oval. 

    It would be great if you could spare a few minutes to answer the following questions and help us understand how the space is currently used and what you would like to see included in the concept plan. This way we can ensure the exciting design meets the needs of the local community.

    All responses must be received by 5pm Tuesday 4 January 2022. We appreciate your feedback and comments.


    Consultation has concluded
    Share on Facebook Share on Twitter Share on Linkedin Email this link
  • CLOSED: This survey has concluded.

    Survey closed

    It would be great if you could spare a few minutes to answer the following questions and help us understand how the space is currently used and what you would like to see included in the concept plan. This way we can ensure the exciting design meets the needs of the local community.

    All responses must be received by 5pm Wednesday 9 June 2021Council appreciates your feedback and comments.

    Consultation has concluded
    Share on Facebook Share on Twitter Share on Linkedin Email this link